Posts

4851 Texas Co Bridge

Image
  Arrived at 8:35am and contractor was getting cranes ready to hookup for Girders, first girder arrived at 10am an hour late. we set the first three by 12:30pm, the next set showed up by 12:50pm. Finish setting all girders by 2:40pm, contractor was going to place Diaphragms before leaving for the week. Will be placing deck panels next week.

4851 Texas Co Bridge

Image
Arrived on site to find out concrete trucks will be late 11:50am First concrete truck showed up, pouring bent 2. Started pouring Intermediate bent after checking elevations  Finish off with pouring bent 1

4851 Texas Co Bridge

Image
Arrived on site at 9:30am, contractor setting up crane to pull deck from bridge Deck cut ready for removal Breaking concrete diaphragm and removing the cut deck panels.

4851 Texas Co Bridge Replacement

Image
  Arrived on site at 7:55am and contractor was delivering equipment and Sub-contractor (Collins & Hermann) was removing old guardrail. Traffic control was in place and Job board was up and all documents were in place. Guardrail being removed. Contractor stated that they will start removing old bridge on Wednesday, he will let me know a time.