4851 Texas Co Bridge

 














Arrived at 8:35am and contractor was getting cranes ready to hookup for Girders, first girder arrived at 10am an hour late. we set the first three by 12:30pm, the next set showed up by 12:50pm. Finish setting all girders by 2:40pm, contractor was going to place Diaphragms before leaving for the week. Will be placing deck panels next week.